Friday, March 9, 2012

DTS Package

Hi -
I'm wondering if there is a way to have an "Execute Packge Task" run even if
the package that triggers it has multiple tasks running simultaneously? So
I
don't want the next package to run until the current package is finished, bu
t
there is not a definite start and end point to the tasks in the current
package...
If I can explain further - I don't know which task will end up running last,
so I can't use the workflow of "on success", "execute the next package"...
ThanksCreate a package that executes all other packages. In this super-package you
can then design an appropriate work flow.
ML
http://milambda.blogspot.com/

No comments: